Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation

Answer Posted / s.rama pandia raj ( asst.manag

i will go with answer of Mr.Adishankar, but i feel a small
suggestion
cement-1
sand-2 with bulking 25% is 2.5
metal- 4
volume of 1m3 of wet concrete is equal 1.54 times of dry
mix

so cement required is 1.54/7=0.22m3 of cement equals 6.34
bags (0.22/0.0347)
sand required is 2.5/7=0.357*1.54=0.55m3 or 0.22*2.5=0.55m3
metal required is 0.22*4=0.88m3
1m3 of 1:2:4 nominal concrete mix contains
cement-6.34 bags
sand - 0.55 m3 with 25% bulking in normal practice
metal - 0.88m3

Is This Answer Correct ?    22 Yes 9 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how much repeitation for conventional and maivan formwork?

1983


How much sand and cement requirement for 1 SQM 125mm thickness Brickwork

4446


Calculation of Pier Cap with tapper area?

6281


How many axes do cartesian coordinate system has?

1051


Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?

2160


why is M30 grade Concrete use for Foothing & Column M50

3430


How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?

1986


What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?

2271


How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?

2006


How much is the cover for slab?

1217


Explain the different types of building contracts?

1057


What is the use of extend command?

1227


in staad ,why we realease a moment of a member ? what is affect if we realease a moment

2209


What are your goals?

2847


Explain the mechanism of cavitations in pipes and drains?

1061