what is right time of slab DE shattering and beam boo tam.
Answer Posted / mitesh patel
Beam Sides can be allowed to be removed on the next day of
casting.
Bottoms should be allowed only after 7 days of casting.
This is practical answer on site otherwise contractors will
run away.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how to calculate the scour depth
what are the changes in concrete pour height as per IS 456, 2009?
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
How much of the strength of concrete comes from post- production curing?
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
What do you meant by gui?
How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?
How to calculate quantity of cement , sand and granite from concrete mix ratio and volume of work
HOW SOON CAN YOU TRAVEL DON TO ANY LOCATION POSTED U?
if we use 1.25 bag of cement 3 pharma metal and 2 pharma crush sand what is the strenghtexpected for RCC column
How much does the leaning tower of pisa lean?
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
What is the use of offset command?
explain fie benefits of using standard terminology in the measurement process
Mention different types of roof systems?