What is the clear distance between a MV panel(rear side) and wall.
Answer Posted / annonymous
it should be such that a person can easily work there and depend on the width of the rear access door for the switchgear which shall be opened before accessing the rear of the panel.
Rear access is mainly required for the cable terminations.
we keep it usually 800mm to 1000mm.
| Is This Answer Correct ? | 7 Yes | 0 No |
Post New Answer View All Answers
What is the loss of transformer of 220kv/11kv, 63/80 MVA and 18.05% impedance
what are the difference between PLC and embedded
placing earthing pit in pathway is correct or wrong??. placing earthing wireGI1/18 inside walls is correct or wrong?. explain!!!
A Generator is in running condition and Rotor earth fault alarm is coming.How to check on line(i.e in running condition) whether there is actual earth fault in rotor or not.
Usually in the L & T make MCC feeders' power circuit,we have BMR after the MAIN CONTACTOR.,can we interchange their position, keeping the control logic same???
Types of test in Switchgears, MCC, NGR and DB's how it should be procced. Can anyone give me the details here or email me to pasuvaraj.k@gmail.com
In ACS 1000 drive we are using 12 pulse converter,why don't use 3 pulse converter.
what is V.L.F. testing of power cable? do you know the voltage ratings, like for what rating and size of cable what rating of V.L.F. testing is used?
When we giving the 3 phase supply to ups system how to coming netural?
We have drive feeding an output contactor for a 5000 hp motor @ 5kV application. The motor FLA is 629amps x 1.25% service factor = 786.25 amps The cable that we current have in place between the drive and the output contactor is 350kcmil- MV-105 (parallel cables). Per the NEC table 310.60 (C) (69). This show the cable ampacity is at 615 amps per cable for a rating of 1230 amps. We have derated the cable for the cable tray and the multiple cables application and our calculations show that after the correction factor factor we are at 922amps. 1230 amps x .75% correction factor factor = 922.5 amps. The customer is driving us to then use another safety factor of .25% off of the already derated cable. Can you please provide a longhand calculation for your solution on this application?
Dear Sir I am living in Jaipur Rajasthan now I did complete my b tech degree in electrical engineering in 2012 Sir how I gate certificate of competency for electrical supervisor
What are the advantages and disadvantages of open loop control system?
we have 3.5MVA-11/6KV transformer. how can we calculate earth fault current and NGR calculation?
sir i had plane to do some project with the base of hopkinson test in AC supply its possible
What does the term power factor shows?