extra how much quantity need to fill the actual excavated
quantity.
Answer Posted / mohd ameen
1m3 compacted = 1.8m3 dry excavated.
| Is This Answer Correct ? | 12 Yes | 3 No |
Post New Answer View All Answers
what are the duties of Site Engineer in work site?
what is anchorage length,lap length and (dont remember the last one)
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
How you can use different dimension tools in cad? What are the different dimensions available?
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2
Use of coping on terrace wall and in 4" wall is compulsory or not ?
What tor stands for in tor steel?
how clculate excavated or backfilling quantity by simpson's rule
1.what type of the rock is most suitable for wet mix macadam in construction of road? 2.what is the highest maximum dry density and optimum moisture content can be acheive by using most suitable crush rock?
Why are separation membranes used between concrete pavement slab and sub-base?
how we check the thickness and line of ceiling plaster.
How to check slab shuttering level.? Or check list for slab ?
Why does the pressure increase under soil?
What are the ingredients of pre-stressed concrete?