what is right time of slab DE shattering and beam boo tam.
Answer Posted / ronak shah
as per IS 456 beam bottome should be remove after 14 days.
concrete strength is more than 70%. if span is more than 11
mt then its remove after 21 days.
| Is This Answer Correct ? | 12 Yes | 1 No |
Post New Answer View All Answers
What is dead load impact load live load
why does the most of civil engg is not intersted to going for teaching field?
how much of the strength comes from post-production curing
How do we determine the specific gravity of a cement?
1.what type of the rock is most suitable for wet mix macadam in construction of road? 2.what is the highest maximum dry density and optimum moisture content can be acheive by using most suitable crush rock?
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?
What is absolute coordinates?
PL.tell me about civil engineering questions with answer
what is right & short method of measurement of slab&beam
How will drive weight formula for circular cylinder steel bar in kg/ m please step by step drive?
TELL ME THE EQUATION FOR OGEE SPILLWAY
how to design and calculate materail quantity for concrete speedbreaker ?
what is pile and deam foundation
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.