what is the percentage of binding wire required for 1 mt of
steel binding in gerally
Answer Posted / satya.mvvs
In bridges wastage is very less, so 8 to 9Kgs (.8% to .9%)
may be preferred.
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
what is difference between GTS bench mark and temporary bench mark
How to determine dia of steel for use in column,slab etc. i mean how to calculate the diameter of steel which is to be used in structures.
For a washout valve why are two gate valves required in normal practice?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
Please tell me vasthu room sizes. Thanks.
what is the water cement ratio of 1:6 and 1:4 cement sand mortar. reply soon
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What is GSB gradation
How many types of slabs are there & how to design it?
difference between trapezoidal and pedestal footing and how the load acts on that
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
Mention different types of roof systems?
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.