Why two main buses and one transfer bus scheme not using
for 400kV switchyard
Answer Posted / furqan ahmad
in one and halfbreker scheme scheme both breaker and bus
maintenance is possible.even though this scheme is costly
as compared to other schemes but becoz of reliability and
redundancy it is usually used for 400 kv switchyard
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
can u give me a brief idea about power line carrier communication ??
What are the difference between CT/PT operated Meter and RRAMR Meter for HT/LT application?
11 kg trivevter meter has rating of -/5amps. And pt ratio11000/110v and is connected with 11kv ct/pt unit of cr ratio 75/5amps. And pt ratio of 11000/110v while checking accuracy of meter with HT Accuchek meter what value of PT ratio and CT ratio to be filled in Accuchek meter
How to check the cable fault / hv test of transformer cable.
Lt motor sfu flashing reasons?
a starter used for squirrel cage induction motor?
which protection used in power plant?
what would happen if reactive power (kvar)is increased (more)or decreased (less)? how much exact reactive power should be maintained? and what should be done for that
what is rating boiler
pls,send the previous year written test questions.
which type of questions asking for solar companies?
explain why core loss of a transformer is almost constant under different load conditions when connected across a constant voltage and constant frequency.
Consider three heater bank connected in 3 phase star with neutral.Each heater bank connected in each phase.So each phase get 230 volts supply.my question is,during balance condition, current flow in neutral or Not
I WANT TO know WHICH WAY IS BETTER FOR CONNECTION BETWEEN POWER TRANSFORMER AND MAIN DISTRIBUTION PANEL. 1-IS BETTER WE USE CABLE? 2-IS BETTER WE USE BUS DUCT? my transformer rate power is 2500KVA
How PADO software increase the efficiency of power plant?