Why two main buses and one transfer bus scheme not using
for 400kV switchyard
Answer Posted / furqan ahmad
in one and halfbreker scheme scheme both breaker and bus
maintenance is possible.even though this scheme is costly
as compared to other schemes but becoz of reliability and
redundancy it is usually used for 400 kv switchyard
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What are steps to be taken while designing of DYN11 distribution transformer to achieve magnetising balance?
what about GD square and its important for motor design?
What is meant by reset level of the relay?
What is the minimum distance to be maintained in between HT panel and LT panel and Instrument panel as per IEC and NEC standards?
temp of cast resin 1500kva tx formerwent up to 138.c but came down very fast to about 100.c within 20 mins when load was reduced from 70% to 60%
what is the stear deltaprinceple?
1)What is a Triode? What are its uses? 2) What is a Triac? 3) What is a Thyristor?
What is difference between Sample test and Routine test in safety standard?
As a electrical engineer.. what are the basic norms should follow in transformer oil testing.. 1.What is the Electrode type? 2.How long time you will give for oil testing?
What is knee point voltage of transformer?
PLEASE SEND THE PREVIOUS YEARS QUESTION PAPERS OF RRB JUNIOR ENGINEER-ELECTRICAL
Dear sir, I completed DECE In the year 1995.Now i am working in a private company from last 10 years as an Electrical supervisor.The company having a 1000 KVA transformer.Now i try to apply "C" Licence. I am eligible or not.If not eligible,pls give solution.
design a LV scheme for a 15 storied building?
hai iam arunkumar. i have applied for an section enginner in rrb. i want lat 5 years solved question papers. if u have please sedn it to arun30682@gmail.com
What are the types of power in electrical power?