How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help
Answer Posted / y.singh, b.tech., nit jaipur
For 100 sqm dry volume of mortar is= 2cum in wall and 1.8
in ceiling
Now suppose mortar ratio is 1:4
than cement is=(2/1+4)*1=0.4cum=0.4/0.035=11.42 begs for
100 sqm
Now your reuirement is= 300sqft=27.88sqm
so consumption is=(27.88*11.42)/100=3.18 begs
Ref: B.N.Dutta
| Is This Answer Correct ? | 2 Yes | 2 No |
Post New Answer View All Answers
.5Ast
HOW SOON CAN YOU TRAVEL DON TO ANY LOCATION POSTED U?
RR masonry rate analysis
what is labour consume factor in residential projects
What is difference between combin footing & rapt footing
Explain what are the phases inspections are done by local authority while construction?
How much cement and water required for cement selery????
What is the substitute of Mastic Asphalt?
The 4 main factors to start a construction project are––
Are cruise ships built for the transatlantic run?
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
What is meaning of tlc
In Abutment walls (A1 side) why we are adopting fixed bearing (POT-PTFE)?
Why was the empire state building made of steel?
what is conrete grade ,how are depent on concrete grad and size of concrete?