1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / syed muhsin.s
Bricks- 417 nos
Cement- 53 kg
Sand - 0.3 cum
mortor thickness deducted to be done.
u want to know how it comes????
| Is This Answer Correct ? | 10 Yes | 19 No |
Post New Answer View All Answers
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
What are the reasons for geotechnical site investigations in uganda?
for a column of size 400*230mm column reinforcement= 8-20x(cant write the symbol,i hope u guys undersstand,something like (fi) column stirups=8x@(4l) 230c/c 1)what does these mean 2)how to calculate quantity of steel for this column(ceiling height 11 ft)
Moisture content calculation for diff mix ratio's ??
Define What is rigging?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
Explain what are the skills required to become an architect?
how to calculate the strength of rebound hammer test reading in building construction ?
What is the difference between undo & redo?
The mixture of different ingredients of cement is burnt at?
Which code is used for tor & tmt steel bar?
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
what is meant by residual strain?