1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / hussain
Volume of 1 Brick = 0.230*0.115*0.075 = 0.002
So No of brick req for 1 m3 = (1/0.002) = 500 Nos
1.7 bag of Cement required
0.31 cum sand required for 1 cum of brickwork
Is This Answer Correct ? | 717 Yes | 234 No |
Post New Answer View All Answers
What is Heavy Concrete & Normal Concrete
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
explain the advantages of total stasion
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
How do you calculate reinforcement weight of steel?
How do you change a dimension value in solidsworks?
Slump Values for works?
Define What is an ice dam sock?
how much shouid be the rate for ready mix concrete per cubic meter
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
how to calculate the concrete mix m30 by volume
Why are separation membranes used between concrete pavement slab and sub-base?
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
How can we convert weight batch to volume batch for m30 mix
if 20mm aggregate is coming by weight 25 ton in a 10 wheeler hywa ,then what will be total volume of aggregate in cubic feet.