Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"

Answer Posted / hussain

Volume of 1 Brick = 0.230*0.115*0.075 = 0.002
So No of brick req for 1 m3 = (1/0.002) = 500 Nos

1.7 bag of Cement required

0.31 cum sand required for 1 cum of brickwork

Is This Answer Correct ?    717 Yes 234 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Does brick grows bigger every year?

1199


Please design 12.5m long dubbly beam

1948


how to calculate total cost for slab 35'×8'

1967


what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?

2326


How do you calculate the unit weight of concrete?

1171


HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?

2244


why is the column design?

2310


I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.

2149


Write short note on construction programme for pile foundation.

5472


Why Is Propping Required For Long Structures Once The Form Work Is Removed?

1317


show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation

2225


how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?

1665


what is diversion?

2265


What is command line?

1236


plumbing CPVC fitting FTE Brass full form

2744