IF we have 500kva transformer 11.0/0.415V, 50Hz. How to
calculate the current on HT & LT side, how can we consider
for its breaker (HT & LT both)? You are requested to solve
the question herewith.
Answer Posted / antaratara ghosh
current on HV side= 500/(1.732*11)
= 26.24 A
current on LV side= 500/(1.732*0.415)
= 695.6 A
Breaker on HV side will be 630 A VCB (since it is the
lowest available VCB and in HV side you have to go for
VCB/SF6)
Breaker on LV side will be =greater than (1.2*695.6)A i.e.
834.72 A
so we consider it to be 1000 A ACB
Is This Answer Correct ? | 19 Yes | 3 No |
Post New Answer View All Answers
Why does the adjacent zone of protection overlap?
in my working site. momentary jerck in electrical supply ocurred frequently which cause of multiple losses in our electrical equipements. how can we protect our electrical machines and equipements in this situation.
what are factors to be consider to design a HT & LT motor?
i have interview in Pepsi company what type of question will ask please send the question and answeer
what is the difference between earth leakage and earth fault?
what is the use of piston rings in the engine used for a generator...........
in dc shunt motor if field winding is shorted then
How efficiency of thermal plant can be improved?
give me a clear defination of inductance,and how can u calculate inductance of a motor
11KV AND 22KV NETWORK KW CAPACITY IN RING AND RADIAL?
3 phase induction motor connection star or delta while using ac drive motor is .75 to 5.5 kw
I have an existing old MCCB. ABB Model SACE, the rating are: Ue = 660 volts, Iu =1250 Amps, 3 poles, Ith (max) =800 amps at 45 deg C. I need a circuit breaker for my 3 phase motors, 380 volts 60 hz. the supplier required the minimum ampacity of the breaker to be 911 amps. can i use this breaker with rating of Iu =1250 amps but Ith = 800amps maximum?
how can we say that stator magnetic field rotates with synchronous speed?can we derive?
which protection function should measure RMS value of current&DFT value of current?
Is it required to lay GI wires along with GI/MS conduits from one point to another point though separate earthing cable is conncted from DB to Socket?