during fault conditions the fault current fed from transformer neutral.So the earth pit which is connected to neutral has to supply fault current.
supplying of quantity of fault current by earth pit has limitations such as soil type.CIPipe lengh etc.
if you connect neutral earth pit to substation mat, the mat will supply the fault current.
it is just like earth as big water reservoir and water as current. If more and more parlel pipe lines are laid more quantity of water can be dischrged quickly.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Is it required to do earthing in 2nd shop if earthed armoured cable is laid from 1st shop ?
how to calculate percentage impedence at 75 deg C at normal tap
I WANT TO INSTALL LIGHTING ARRESTOR ABOVE 20 FEET HEIGHT INDUSTRIAL BUILDING. NOW IT WAS 15 FEET HEIGHT HOW MUCH DISTANCE IT WILL COVER & HOW TO CALCULAT THE DISTANCE COVER BY THE ARRESTOR
Dear Mr B C pal...Can you plz. put some light on principle of operation of Z-Ct in conjunction to its use with 1Cx1000Sqmm HT Cables & Directional Ground Fault / Over Voltage Relays...Regd..Parag v K 9899115632
How to decide CT & PT ratings for a given transmission line carrying some rated voltage?
how can i find cable size from current rating?
In siemens S7-300 PLC, what is function and function block ? What is the difference between them ? When to use function and when to use function block ?
how invertor convert the dc into ac give brif detail
Circuit diagram of tube light without starter using electrical choke
What do you mean by distribution transformers?
where solid grounding and where grounding through ngr done and why?
i m in need of current rating chart of heavy duty pvc/xlpe, cu/al cables. can somebody provide me? if yes, plz send me at ashish_patel111@yahoo.com
What is the equivalent circuit of a transformer and its vector diagram?
can we do the star delta connection of capacitor for 3- phase motor starter.
In siemens PLC, why do we want to move the data ?