Answer Posted / sjtbehera
go for bar bending schedule, obtain dia wise reinforcement
also trackout what weight are come to site. then it gives
the balance avialiable at site.
this is the reconciliation of steel.
| Is This Answer Correct ? | 16 Yes | 11 No |
Post New Answer View All Answers
Please Clear My doubt . We Can Design the size of the beam by manually by the Length of the beam...What is the technique adopted
what is right & short method of measurement of slab&beam
how to calcualate the amount of stone,cement,sand required for 1cum of 450mm thick ruble stond masonary with ratio1:5, please me an answer with dtailed step
afe or not
what are the values of compressieve strenght?
What are the different types of foundation?
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
what will happen if one could not properly follow the spacing of slab reinforcement bar?
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
Define line type?
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
3. A vane 12.5 cm long, 8.8 cm dia was pressed into a soft clay at the bottom of borehole. Torque was applied and the value at failure was 55 N-m. find the shear strength of the clay on a horizontal plane.