what is the cutting length of 90 degree bend in four corner
ring in column of 8mm dia size of column 450mmx250mm of
clear cover 20mm?
Answer Posted / ganesan k
410*2+210*2=1240
bend 10*dia,10*8=80*4=240
cutting lenth=1480
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.
what are RIB slabs explain about it
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
Explain soil analysis?
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
what is your role of in previous company as a construction manager
Define What is the tallest man made structure in the world?
For Granite Flooring,For Cement Slurry purpose which one is effective of cost control whether OPC or PPC or White cement?
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
What expenses counted in contingencies and how much it is in related to built-up area of the building.
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.