Answer Posted / hardip dodiya
For Protection of Breaker and protection of EHV Bus-bar in
EHV and HV switchyard. all S/s breaker have one NO/NC
Contact connected to Bus-bar control panel in which. at
time of fault, Breaker Stuck up due to Mechanisam prob or
failure of Trip coil or any mechanical damage problem.
After it TIME-Delay time almost 200ms. busbar control
panels sense this abnormality and give command to all
breaker to trip which is connceted to EHV Bus-bar.
Protect the S/s Equipment.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Give idea about General Engineering. From which book i can study this topic. Pl. reply me via email. My email is ravi@bhelhwr.co.in, also give the name of book/website, from where i can prepare it.
where are the circulat the diesel in DG parts name with pictue
What is the mmf,rgt and ngt please brief completely
what is DRP panels?
What safety precaution are to be taken for avoiding electric hazards ?
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING)IO (current operating)?
What is online and offline ups? how does it works?
State thevenintheorem?
What is the difference between rulling span and wind span of of an Over Head Transmission Line?
HOW TO CALCULATE THE HEAT AND LOAD OF LT-SUBSTATION WHICH CONTAINS 2*1MVA TRANSFORMERS,LT SWITCH BOARD,MLDB,ACB,BUSBAR,ETC...?
how many load we can take for lighting
what is 3rd Harmonics? how it is generated in alternator
Between educational qualification and practical work experience, give us a brief explanation on your practical experience in your past Endeavour that you performed well to the satisfaction of your past or present employer?
How to set the relay,,??
how open delta PT works & what is its construction?