Why we do design mix of concrete when there is nominal
method using the IS-Code available ?
Answer Posted / elanthendral m.
Proportions for Nominal Mix-Concrete:
Nominal mix concrete may be used for concrete of M 20 or
lower. The proportions of materials for nominal mix
concrete shall be in accordance with table no 9 (IS 456-
2000)
above M20 grade we have to go for mix design produces as
per IS 10262-2009.
all the batching should be veigh batching only
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
can i get hindi version of is codes based on civil engineering?
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
What is the difference between Grade I, II and III of GSB?
How you can use different dimension tools in cad? What are the different dimensions available?
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
What is meant by dimensioning?
I am called for interview from north east power plant .so, I need some interview question which may help me.
how many minimum admixtures are used in water froofing structures
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
How many types of slabs are there & how to design it?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
Difference between pre-tensioning and post-tensioning.
to minimize budget cost of building , what can i do
Explain moment of inertia and its importance.