Answer Posted / ramachandra reddy
On TRANSFORMER OIL BREAK DOWN VOLTAGE test is carried out which is done on field while filling the oil in transformer. This process is also called oil filtration.
1.Take sample from top of Transformer before filtration.
2.The BDV of oil should withstood min 50 KV
3.The gap between the test electrodes sample to be 2.5mm maintained
4.At least 5 sample(top/bottom) should be checked separately while filtration.
5. The samples should withstand 50 kv for 1 min.
5. Take the average of all the samples timings.You will get value.
7.Procedure
a.Voltage should be gradually increased from 0.
b. At one point Flash will take place and that point is
termed as Bread down Voltage
| Is This Answer Correct ? | 26 Yes | 4 No |
Post New Answer View All Answers
If the line voltage is reduced to 75% of its rated value then by what percentage current will reduce ?? 75% 25% 50% no change and why ?
what is 30-phase of transformer
Please define ampere?
in battery charging room we find two fuses (one in positive other in negative cables ).why it is so?one fuse is ore than sufficient?
DG cranking voltage?
What test must you do before powering up a circuit that you have been working on?
What is superposition theorem?
What fomula is used to calculate: 1. rated frequency withstand voltage, and 2. rated lightning impulse withstand voltage.
what is mean by restructuring power system?
what are the installation procedure of high voltage power transformer,CT,CB&PT?
Explain the different methods used in the choice of rotor slots for reduction of harmonic torques in an induction motor.
What are the criteria shall be considers for sizing Fuse and MCB? If the rated current is 10Amps what should be the fuse size / MCB Size?
What is meant by sag?
dg earth connect only in the amf panel or not why
how flow current in 220 kv line to line