How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help
Answer Posted / umair ahmad
unit of rate=300sft
thickness of plaster=12mm
wet volume of mortar=300*0.039=11.7cft
dry volume of mortar=11.7*1.27=14.85cft
ratio of cement=1:4(Assuming 1:4 ratio of mortar)
sum of ratio=1+4=5
quantity of cement=1/5*14.85=2.97cft.
2.97/1.25=2.376 Bags.
quantity of sand=4/8*14.85=7.425cft.
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
What is Gsb tollens ?
Please tell me vasthu room sizes. Thanks.
Minimum and maximum size of the building components
The 4 main factors to start a construction project are––
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?
Explain what is alternate bid?
how much quantity of cement,sand and water required for 1 sq feet flooring work .
Gidc technical que paper
how to nfind out the specific gravity of sand.aggregate,water please help...
in the construction of residential building what type of tank are used?where?why & what is its purpose?
What are the disadvantages while using stone dust as filler in pavements?
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
What is braced excavation all about?
What is soil enforcement?