How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help
Answer Posted / umair ahmad
unit of rate=300sft
thickness of plaster=12mm
wet volume of mortar=300*0.039=11.7cft
dry volume of mortar=11.7*1.27=14.85cft
ratio of cement=1:4(Assuming 1:4 ratio of mortar)
sum of ratio=1+4=5
quantity of cement=1/5*14.85=2.97cft.
2.97/1.25=2.376 Bags.
quantity of sand=4/8*14.85=7.425cft.
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
How much area will be covered in 1 litre of Velvet touch paint in normal wall condition
what is the types of surveying?which type of survey carrying for type of work?
can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
how to control PQI (Project Quality Index)
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
how to shuttering is used in slab
In earth work 1300 cum soil how to calculate how many liters require in water
How many Sft of Level Plaster per Kg
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
Define What is the tallest man made structure in the world?
what is the painting co efficient of slope roof tiles?
Define What materials were used to build the Golden Gate Bridge?
explain five benefits of using standard terminology in the measurement process?