how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / arun
DETAILS:
cement = 1,
sand = 2
metal = 4
so wat is the ratio we want mixing (1:2:4)=1+2+4=7
7 is mixing propotion
volume of wet cement conceret is 1.54 to 1.57
unit weigth of cement is 1440kg/cum
one bag of cement =50/1440=0.034722 cum
solution : cement = 1.54/7=0.22
0.22/0.03472=6.33 bags
one bag of cement = 50kgs
=6.33*50kgs=316.82 kgs
solution of sand = 0.22*2=0.44cum
2 is the mixing of propotion
soolution of metal = 0.22*4=0.88cum
4 is the mixing of propotion
say i cum of cement conceret 1:2:4 ratio
cement = 6.33 bags
sand = 0.46 cums
metal = 0.88 cums
this is one type of solution
unit weight of cement is 1440kg/cum
sand 1660 to 1800kg/cum
Unit weight of metal is 1630kg to 2000kg/cum
so cenment = 1.54/7=0.22
0.22*1440=316.82 kgs/cum
sand = 0.44*1750=770kgs/cum
metal = 0.88*2000=1760kgs/cum
| Is This Answer Correct ? | 92 Yes | 21 No |
Post New Answer View All Answers
For what purpose bedding is used under storm water drains?
how to calculate total cost for slab 35'×8'
What is an object snap mode?
How to identify the vitrified tile and ceramic tile by observation only after executing the job.
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m
What is construction mitigation management?
Does degree of bend of rebars has any effect on strength of the member? For example- if a beam is designed with 45 degree bent up bar with respect to architechtural needs and is not 45 in practical so will there be any reduction in the strength of member?
What does civil engineering mean?
What do we mean by partial moment release ??
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Bitumen grades are 30-40,60-70, 80-100. what is mean by 30- 40
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
what does the grad of cement shows (denotes)?
what will be price of 1:2:4pcc per kg?
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building