how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / arun
DETAILS:
cement = 1,
sand = 2
metal = 4
so wat is the ratio we want mixing (1:2:4)=1+2+4=7
7 is mixing propotion
volume of wet cement conceret is 1.54 to 1.57
unit weigth of cement is 1440kg/cum
one bag of cement =50/1440=0.034722 cum
solution : cement = 1.54/7=0.22
0.22/0.03472=6.33 bags
one bag of cement = 50kgs
=6.33*50kgs=316.82 kgs
solution of sand = 0.22*2=0.44cum
2 is the mixing of propotion
soolution of metal = 0.22*4=0.88cum
4 is the mixing of propotion
say i cum of cement conceret 1:2:4 ratio
cement = 6.33 bags
sand = 0.46 cums
metal = 0.88 cums
this is one type of solution
unit weight of cement is 1440kg/cum
sand 1660 to 1800kg/cum
Unit weight of metal is 1630kg to 2000kg/cum
so cenment = 1.54/7=0.22
0.22*1440=316.82 kgs/cum
sand = 0.44*1750=770kgs/cum
metal = 0.88*2000=1760kgs/cum
| Is This Answer Correct ? | 92 Yes | 21 No |
Post New Answer View All Answers
Define What is the force exerted by the Tacoma narrows bridge?
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
Which is the best book for building construction?
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
What are the different methods for drawing an arc?
What is the method of soil replacement test?
Special thing in designing a overhead reservoir ? which is different from an ordinary design
if 20mm aggregate is coming by weight 25 ton in a 10 wheeler hywa ,then what will be total volume of aggregate in cubic feet.
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building
How many % we consider for lap for reinforcement for estimates
What is specific gravity???
what is civil enginnering & what you need of this course?