If the load of transformer is getting more than its
rating,,,than how to overcome this problem? Suppose thee
rating of transformer is 315kva and the load is going
beyond than the rating say around load: 352kva...
Than how can we solve this problem without deducting the
load.
Answer Posted / ch.nikhil
first of all check whether the txer is taking load on its
two phase or 3 phse ...And arranging the proper cooling to
the txer at lst fr 15 min and check the load will become
less or not by reducing its temp this one solution (or)
check the aproximate relay setting whether it was acting or
not and the txer must be tripped and the proper testing like
ratio test and sht ckt tst must be conducted.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
WE know that for Inductor X=2pifL,In DC f=0,then X=0 so,V=IX=0;But In the DC excitation of rotor of AC generator,DC motor field coil which coils are inductor so why does not applying DC voltage short the rotor coil of AC generator and field coil of motor?If it would then DC source might be damaged but it is not happened. Why does the strand conductor of Electrical power transmission line make twist?
What are the advantages of hydropower?
The efficiency of a 100kva transformer is 0.98 at full load as well as half load , for this transformer what is the Copper loss at full load ?
If any one's require of phoenix contact like( relay , termilnal block , surge protection device ) , product please contect me 09878206357 chetan verma
If a air condition consume 2.50 to 3.00 amp then how much it will consume in watts if it is running 10 hours out of 24 hours????
what is the profesional board for electrical engineer what is thepast and during construction for electrical engineering
What are the different sign conventions used in electric circuits?
how we control automatic generator i'e with to supply (main supply and local generator) when the main supply was break to supply the local supply automatically to begin supplying power.I now this control circuit is the combination of contactor time delay contactor switch and overload relay .but my question is how we combine those component thank you
Dear all, I'm manikandan I have done by DIPLOMA EEE from 2011 , I have 5 years of experience from Power plant instrumentation field , which one field is give long life & which one field is best ,I confused a lot and also I'm studying AMIE, can I choose which department from Section B examination? pls tell me
Two bulbs of 100w and 40w respectively connected in series across a 230v supply which bulb will glow bright and why?
HOW TO WORK A VFD?SAY SIMPLE METHOD
I have 1500/1A CT If i connect this CT in 6.6KV bus bar means what will be the voltage present in CT?
How to design a Unit auxiliary transformer for a power house having a unit of 65 MW and Generating voltage of 11 KV and Secondary voltage of 433V
Air refrigeration cycle works on the
what are the breakdown voltage rating of mini- curcuit'transfarmer!