how to calculate rate analysis of M25 grade concrete
Answer Posted / k v arjuna rao
As per material availability the ratio's of Sand Aggregate
and Cement including admixers calcuted per cum by design
mix.
The quantites of these material is multiplied with existing
rates including Transportation charges we get the Material
cost per Cum.
Then Labour required per cum is calcuted as per CPWD
Standards and multiplied with local labour rates given by
State Govt SSR or CPWD SSR for that area. we get labour
Rate for 1 Cum.
Finally add hire charges of machinery used for mixing and
pumping and placing of concrte, Sunderies, water charges &
Overheads & Profit for contractor on Material rate & labour
rate.
finally we get Rate per Cum.
| Is This Answer Correct ? | 20 Yes | 8 No |
Post New Answer View All Answers
Are you ready to relocate with your immediate family to United States as a new employee?
Difference between lime, distemper and plastic emulsion?
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
Rate analysis for construction of a solid block masonary of size 400x200x200 in C.M.1:5 in superstructure .Compressive strength 5.00 N/Sq.mm Confirming to IS: 12894:1990, with necessary scaffolding, raking of joints and pointing the same. I require rate per Cum.
Can we use concrete of slump cone in cube casting in which we have already measured slump?
I am practising engineer. I am searching for tutorial of RCC T Girder design Example in staad pro.Do anybody has this?please help
What are segregation and bleeding?
Explain what is 1/8 on the architect ruler denotes?
At what point does a circle start losing area when being flattened?
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
what is differences between ferrock and concrete ?
Civil engineering related
i need gate exam civil engineering question papers with answers