how to calculate steel quantity in plinth beam&footing
Answer Posted / maruthu
whatever it is you see the drawing . say for example
footing 1.2m* 1.2m. 12mm rod 200mm c/c. basic formula
D^2/162 PER 1m length 12^2/162=0.888,size of rod 40' or
12.2m. so 0.888*12.2= 10.83kg per12mm rod.
1.2/.2=6+1=7rods.size 1.2-cover 2sides . 1.2-2[.04]=1.12.
1.12*7=7.84*2=15.68m b'coz 2sides mat.
15.68*.888=13.92kg requirement for 1.2*1.2m footing.
| Is This Answer Correct ? | 43 Yes | 7 No |
Post New Answer View All Answers
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
Describe a time when you anticipated potential problems and developed Preventive measures
natucher of concrete &type of concrete?
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
What is horizon or horizontal mining?
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
it is a corrected question." make a list of engineering property(properties) of soil.
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
cement required for construction of 400mm*200mm*200mm concrete solid blocks for 1sq.mtrs,how?
What is the general specifications of a bituminous pavement road?
What quantity of 1.0 m3 bricks required?
silt%= silt volume/ silt+sand volume is this right?
What are the advantages and disadvantages of using plastic and timber fenders?