in one substation we have two power transformers of
100mva,75mva capacity.statoin load is155mva.how much each
tranformers share the load????
Answer Posted / k.prakashchandra
The voltage drops in the transformers + line should be equal
at the secondary bus-bar. Current shared by tr1 x its %
impedance = load shared by tr2 x its % impedance.Hence The
load sharing ratio is inverse to ratio of % impedances.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Efficient electrical earthing in hard rock area
List few applications of d.c series motor?
Why are lt windings placed near the core?
why it is so called as xlpe(cross linked poly ethyline) cable?
What do you understand by avr?
what is the eight bit unit?
what is the reason for indication of light in the earth lamps of main switchboard.if there is an earth why does one lamp get dim and the other two bright.
In india, according to trade theory above 5 HP motor reqired star delta starter. But we R connect 11 KV motor with 14MW in Direct to line ( With VCB starter combination) Can U Guess, How it is possible ?????
why it is not advisable to run low rating (19KVA) DG sets in parallel for long durations even though they are provided with droop ckts (QDC)
What is the main cause of magnetism?
I want to put this query to SENIOR & EXPERIENCED ELECTRICAL ENGINEERS. 1)I want to know about the control circuit diagrams for control panels. I found it difficult to understand. Is there ant booklet through which we can learn the circuit diagrams? 2)I want to learn about conduiting, laying cables, preparing cable schedules and various techniques which is the part of building infrastucture(construction field). I don't have any experience in this area. I have experience in control panels only. that's why i am not getting any opening in building infrastucture (construction field).Can I get the job in this field as Trainee Engineer? How to enter this field? I need job in PUNE
How much load can take a 16 mm aluminum cable 3 phase
what is apparent poewr, reactive power, & active power?
what is LSR?
If 100 KAV USP dedicated earth got disconnect / Cut. What will happen at load.