What is ideal location for cube casting, RMC vehical at
Ground Floor and Slab casting at 40th Floor
Answer Posted / sudhir shetty
Its at the ground floor because during pumping there will be
some loss of slurry etc which is calculated during designing
of structure after which required strength is calculated. If
its taken in 40th floor u will not get the perfect sampling.
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
How high should the water tank be to provide a 60 psi at base of this water tower?
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?
what are the five benefits of using standard terminology in the measurement process?
Test procedure of fly ash bricks as per code ?
in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
Explain what is 1/8 on the architect ruler denotes?
HOW SOON CAN YOU TRAVEL DON TO ANY LOCATION POSTED U?
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
if we use 1.25 bag of cement 3 pharma metal and 2 pharma crush sand what is the strenghtexpected for RCC column
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?
what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?