Answer Posted / balakrishna bedudoori
I think the ideal location for cube casting is near Slab
casting at 40th floor, because if we take concrete from RMC
vehicle at ground floor, free falling height of concrete
from the vehicle to the ground is generally more than 1.5m,
which can lead to seggregation of concrete, which is not
good for taking moulds.
| Is This Answer Correct ? | 5 Yes | 4 No |
Post New Answer View All Answers
If 40 backlogs are cleared m finally with 65 percent marks . Am I eligible to get visa to US
how many running meters in one kilogram of 4mm pvc coated chainlink fencing
I am called for interview from north east power plant .so, I need some interview question which may help me.
I need old MMUP exam question and answer for Civil engineering
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx
Explain the water bound macadam roag
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
detailed calculation of the amount of cement used?
How to increase a bearing capacity of soil?
How to testing voids of filled aggregate in bitumen mix design
How to calculate woden area in sft and Cft
what are the types of dimensioning?