how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / pervaiz
we have total 731 cu.ft
Now calculating
Cement
1/4x1.54x731 = 281.43/1.25 = 225.14 bags
Sand
1/4x1.54x731 = 281.43 cuft
Crush
2/4x1.54x731=562.87 cu.ft
Now verifying
Is This Answer Correct ? | 5 Yes | 10 No |
Post New Answer View All Answers
Coverage of 25mm.thick ratio of 1:4 cement mortar?
five benefits of using standard terminology in the measurement process
What things you need to take care of before building a kitchen island?
please briefly explain calculating or estimating steel quantity for a RCC column?
What Reinforcements Are Used In The Process Of Prestressing?
Water filter calculation formula
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
What is the primary difference between adsorption and absorption?
pls give me ans to ACT formula cube testing porpuse
How to calculate the load of partion in flat slab if we use brick?
step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed
how do you stabilize a waterlogged area in road construction
how to do sudoko puzaals?
how to diffenentiate the fixed beam and simply supported beam in the execution while reading the drawing and how the reinforcement detail will be differ for the above.
material required for construction of 1cu.mtr wall (Cement, No of bricks (Brick size 40cm x 20cm x 10cm),sand,Quantity of water