how many cement use for 1cum concrete for 25Grade.

Answer Posted / vidyasagar daley

from m10 to m20 are consider as nominal mix but m25 is
design mix .the ratio is also may consider as 1:1:2

calculation:

for 1cum concrete required fine,coarse aggregates are
0.46cum-fine aggregate and coarse aggregate is 0.92cum.

1(cement)/1(sand)x0.46x1440(cement
wt.kg/cum)=662kgs.or13.248bag.
(or)

25 grade mix design is 1:1:2
total = 4
cement is 1 part =1/4 = 0.25 m3 of cement
1m3 of cement =1440 kg
0.25 m3= 360 kg

Is This Answer Correct ?    20 Yes 19 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2

2398


crank types

1886


Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?

2042


what is detail procedure of eccentric footing? plz. give solved exmple?

1838


SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?

2251






cause of cylinder test failure

2836


Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot

1833


What is meant by autocad?

665


Why should pumping be not used in case of concreting works?

999


what is mc arther pile?

1784


how much need sand and cement for 1 cft roof construction?

3969


what is a well

1509


How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure

1774


How you can turn off the display for dimension in CAD?

642


in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh

1717