Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation

Answer Posted / m

ratio is 1:2:4
1+2+4=7

100cft concrete
100*1.54=
then divide by 7
then divide by 1.25 you wil have cement bag

Is This Answer Correct ?    71 Yes 29 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How much sand and cement requirement for 1 SQM 125mm thickness Brickwork

4553


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

2913


Why was the empire state building made of steel?

1189


for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.

2077


What is braced excavation all about?

1201


What is the difference between EPC,DBOOT and BOOT.

25038


how clculate excavated or backfilling quantity by simpson's rule

5185


use ofr concrete as per grade ?

2125


Define What materials were used to build the Golden Gate Bridge?

1165


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

2499


how to calculate the material from ratio of work PCC, RRM,POINTING, RCC

2695


hi, i am doing my B.tech third year and i want to have a job in Genpact...So can you help me which kind of job would be more appropriate for me in such a company and How should i prepare for an interview?

2398


calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick

1854


What are your goals?

2993


How to decide/consider the grade of bitumen for dbm.

2283