mix design procedure, i.e m15 to m40
Answer Posted / nitin lahane
Site Laboratory Items necessary on site for Mix Design
1. Set of 12 Cube moulds of size 150 x 150 x 150 mm.
2. A slump cone, tamping rod and a scale.
3. Weighing balance of 5Kg. With accuracy of 2gms and corresponding weights up
to 2 gm. Electronic Balance is highly recommended.
4. Spring balance of 100Kgs.
5. Milk cans of 5,2 & 1 litre capacity for addition of water.
6. 250 ml measuring cylinder for silt test.
7. Set of sieves as under:
40mm, 25mm, 20mm, 12.5mm, 10mm along with a Pan & 4.75mm, 2.36mm,
1.18mm, 600 μ, 300 μ, 150 μ, 75 μ along with a pan and lid.
8. Conical cans of 5 lit and 1 lit capacity for calibration.
9. If Weigh Batcher is not available at site, then following Farmas should be made
available at site:
Capacity in litres Nos. L B H Size (in cm)
35 4 40 x 25 x 35
30 1 40 x 25 x 30
25 2 40 x 25 x 25
20 1 40 x 25 x 20
15 1 40 x 25 x 15
10 2 40 x 25 x 10
10. Hot plate
11. Compression testing machine.
12. A yield box of size 50cm x 50cm x 75 cm made of mild steel or plywood.
| Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?
a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
In the roof of a pumping station explain briefly the components of a waterproofing system?
explain the advantages of total stasion
One plate (women civil worker lifting Plate - Satti) sand measures how many cubic feet?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Differentiate first angle & third angle projection?
Which IS Code/American Code applied for coupler test of steel
what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
What are the composition of a landfill?
Why are pull-out tests performed for soil nails?
how pumping of concrete effects the quantity of material used in it?
Formula for calculating the volume of bulb in underreamed pile