Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

in our sub station why we step down firstly 33kv\11kv then
11kv to 430v. can we direct step down 33v to 430.v.

Answer Posted / engineering.force

One more important point you all have missed is about the
secondary winding current. If we step down from 33/11 KV the
secondary current will be less than if we step down from 33
KV/440 V, hence the secondary winding has to be accomodated
with above high value of current. This will lead to increase
in winding diameter, thus increasing the overall size of the
transformer, and also increase in the heating of the
secondary, thereby reducing the efficiency of the
transformer. And hence costly. So taking in the above
considerations, we have to design the step down voltage
level so as to make it cost effective and economical.

Is This Answer Correct ?    8 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is zero of the system?

1047


What is the formuala to calculate the rating of motor protection circuit breaker

2168


How many double suspension hardware fittings are required on a double circuit transmission tower?

2041


why the electrolyte level in lead acid battery is maintained 2.5 cms above electrodes?

1814


how wecalculate breaking capcity of acb mcb mccb .explain with example

1860


Why derating factor os applied on Cables?

1900


WHat is the requirement of installing FAST ACTING EARTH SWITCH in GIS and how is that integrated with protection system. How and when does it operate?

2093


Showing results for capital, machinery, stock,wages, carriage in words, salaries, factory rent, repairs, fuel and power, buildings, debtors, sales, purchases, creditors, return outwords, return inwords, drawings, discount allowed, discount receivable, office expenses, bills payable, bills receivable, cash in hand, cash at bank, office rent comes under debit or credit

1462


What is the form name of 'c' license, I want to download in web

1853


What is the equivalent circuit of a transformer and its vector diagram?

2641


How to calculate cable size by using load.?? Any formula...

1315


why Induction Generators are not "Black start" ? and apart from WTGs where this types of generator are generally used?

2595


sir please tel me how calucalte kwh if home taken load 30ams how maney kwh taken per day.and 3phase motor 5hp per hars how maney load teken and how mach kwh and forward me to electrical table for calicalte kwh and kvr and kvah

3897


whats the differece between Exd and Exe

4836


why different series of vfds (like allenbradley)are used in industry ?

2243