What is a BBS?Find out the cutting length for a 300*300 column with 40 mm cover?
Answer Posted / vishal s rao
BBS is Bar Bending schedule
For 300*300 size column
rings will be 300-(40*2)=220mm
220mm on 4sides i.e =880mm
for bending purpose on two end 75mm to be kept.
i.e 880+75+75=1030mm
For right angle 2*d to be added.
i.e 2*8*4=64mm
So totally = 1030+64=1094mm.
| Is This Answer Correct ? | 14 Yes | 22 No |
Post New Answer View All Answers
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
Why are steel plates inserted inside bearings in elastomeric bearings?
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item
how to preaper for interview wat they asked in interview give me idea
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What is a bearing capacity of soil?
What is the maximum strength of cub compress strength in one cub testing
How we can calculate the cement, sand,bricks , water , quintity in 1:6 Ratio 1 cubic metre b/w and 1:4 Ratio in 1 Squre metre b/w????
what is the use in canals of longitudinal drains and cross drains in lining areas?
Define What is the difference between routing maintenance and major maintenance in school facilities?
VAT and CST ? Which benefits for buyer ? Why benefits?
What are the responsibilities of a site manager?
what is cement wastage percentage in NHAI ROAD WORKS
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??