What is difference between nominal mix and design mix?
Answer Posted / girish negi
Nominal Mixes
In the past the specifications for concrete prescribed the
proportions of cement, fine and coarse aggregates. These
mixes of fixed cement-aggregate ratio which ensures adequate
strength are termed nominal mixes. These offer simplicity
and under normal circumstances, have a margin of strength
above that specified. However, due to the variability of mix
ingredients the nominal concrete for a given workability
varies widely in strength.
Designed Mixes
In these mixes the performance of the concrete is specified
by the designer but the mix proportions are determined by
the producer of concrete, except that the minimum cement
content can be laid down. This is most rational approach to
the selection of mix proportions with specific materials in
mind possessing more or less unique characteristics. The
approach results in the production of concrete with the
appropriate properties most economically. However, the
designed mix does not serve as a guide since this does not
guarantee the correct mix proportions for the prescribed
performance.
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
what else we can add rather than admixture in concrete to reduce the cement quantity?
Explain the importance of moment of inertia?
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
silt%= silt volume/ silt+sand volume is this right?
What are the types of slump?
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
PL.tell me about civil engineering questions with answer
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
for a column of size 400*230mm column reinforcement= 8-20x(cant write the symbol,i hope u guys undersstand,something like (fi) column stirups=8x@(4l) 230c/c 1)what does these mean 2)how to calculate quantity of steel for this column(ceiling height 11 ft)
i need gate exam civil engineering question papers with answers
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
can any one explain bar bending schedule of bems and columns and slabs ??
load combinations how many types for staad design purpose?