How to calculate Rate of 10 cum of Brick masonary,if the rate of material are as fallow?
sand=Rs.500/mt
Brick=Rs.5/brick
Labour=Rs 300/day
Free issue=cement+water+electicity.
Answer Posted / dipak d patel
1 Bricks no. 5000.00 005.00 25,000.00
2 Sand cum 2.64 706.00 1,865.72
3 Cement Bag 15.60 000.00 3,120.00
4 Labour Day 16.00 500.00 8,000.00
5 Mason Day 07.00 500.00 3,500.00
6 cont profit, OH to be considered as per your
regualations. Normally 15% to be considered for the same.
Total Rate for 10 cum without contractor's profit is
41,485.72 Rs/10cum.
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
Calculation of curtain wall of box culvert
why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?
What is the largest concrete dam in the world?
Define block?
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
what is mc arther pile?
How to calculate woden area in sft and Cft
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
How can you produce desired alloys and discuss their applications in daily life.
What is the method of soil replacement test?
What is Refuse Area In High Rise Building ?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
How do you maintain water pressure?