How to calculate Rate of 10 cum of Brick masonary,if the rate of material are as fallow?
sand=Rs.500/mt
Brick=Rs.5/brick
Labour=Rs 300/day
Free issue=cement+water+electicity.
Answer Posted / dipak d patel
1 Bricks no. 5000.00 005.00 25,000.00
2 Sand cum 2.64 706.00 1,865.72
3 Cement Bag 15.60 000.00 3,120.00
4 Labour Day 16.00 500.00 8,000.00
5 Mason Day 07.00 500.00 3,500.00
6 cont profit, OH to be considered as per your
regualations. Normally 15% to be considered for the same.
Total Rate for 10 cum without contractor's profit is
41,485.72 Rs/10cum.
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?
Minimum concrete cover in slabs, columns, beams, foundation and other st?
What should be the lap length in raft if height of raft is 0.800mm ...it couldn't b 50D or 40D...we just have to join upper and bottom reinforced...is there any formula for determine it...
which steel is better for residential building tmt steel or hysd steel
What is the diameter of the 3"inch nails?
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
What is the difference between absorption & adsorption and sorption?
why we use 19x9x9and 20x10x10 but not other
Explain what are the problems one might face while having a Cantilever balcony?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
What is the difference between Hinged and pinned in Column ends
In case if concrete box girder bridges how is the number of cells determined?
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
afe or not