how much water you will add to the mix, for making 1 m3 of
concrete to achieve strength of mix 20N/mm2 at 28 days.
Answer Posted / fathi abu sabha
20N/MM2 = 200KG/CM2 CMPRESSIVE STRENGHT
THE WATER FOR 200KG/CM2 = 1/2 OF CEMENT QY 1/2* 200KG = 100
LITTERS
FOR 30N/MM2 = 300 KG/CM2 = 1/2*300KG = 150 LITTERS
| Is This Answer Correct ? | 5 Yes | 10 No |
Post New Answer View All Answers
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
Different sizes of Hollow blocks and its weight. Thanks.
How do you maintain water pressure?
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
what is the metal ratio in granular subbase coarse for one cum ? And please explain the morth table ...what is the difference between grading 1 , 2, 3 what it means..plz explain
Floor tile measurement? Wall to wall or skirting to skirting
what is the water cement ratio? how to calculate it? list the wt. of constructions materials including concrete both ordinary and light wt. concrete
What is 1/8 on the architect ruler denotes?
manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.
Spider cracks occur in beam bottom due to––
why are you joining in this (applied post) job and your aim for this job
how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
What is meant by autocad?