How to calculate Rate of 10 cum of Brick masonary,if the rate of material are as fallow?
sand=Rs.500/mt
Brick=Rs.5/brick
Labour=Rs 300/day
Free issue=cement+water+electicity.
Answer Posted / p.ayyanar
for example 20m length and 5m height.nominal volume 20*.3*5=30
normally motor joint 1cm
Therefore actual volume =20*.29*5=29
standard brick size 20*10*10.NOMINAL SIZE=(29\.20*.10*.10)=14500NOS
no.of bricks per cu m=14500\30=484
5%wastage
so 10 cu m 5000bricks available
| Is This Answer Correct ? | 7 Yes | 3 No |
Post New Answer View All Answers
how many material required for brickbat water proofing of toilets.
What is the Maximum %age of Steel in columns and beams ?
how do you calaculate the total steel quantity of an rcc building using thumb rule?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
How to marking the building
Explain the latest method to detect a crack in a building?
we have a crushing plant and our product is experiencing flakiness and elongation over limit for granite. what is the solution to this problem? how can it be avoided and what to do differently? It is not ok for batching plants
Can inverted beams used in pipes during construction? If yes, explain how it can be implemented?
What is the meaning of a blue land surveyors flag?
What is pre-stressed concrete?
How to determine thee cut length for steel reinforcement bars in R.C.C design
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
Define What happens to Load at yielding ?
In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.
What is the purpose of the gap in the road on this bridge?