I need to plaster an area of 1500 square meter. how much
quantity of cement and sand need for this.?
Answer Posted / mohammed aijaz hussain
Let the thickness of plastering be 12 mm and CM(1:4)
Volume of wet mortar = 12 mm X 1500 sq.m.
= 18 cu.m.
Add 20% for depressions, joints and wastage
= 3.6 + 18 = 21.6 cu.m.
Volume of Dry Mortar = 1.3 X 21.6 = 28.08 cu.m.
Cement required = 1/5 X 28.08 = 5.62 cu.m.
= 160.6 Bags
Sand required = 4/5 X 28.08 = 22.46 cu.m
| Is This Answer Correct ? | 49 Yes | 5 No |
Post New Answer View All Answers
how to calculate the length diamond shaped striupps in column
how to identify the failure of building by expansive soils
How does a traffic light signal work ?
Minimum and maximum size of the building components
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
What does civil status mean?
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
How do you compute volume of airflow?
How to fix toll charge for a particular vehicle at toll booths in a highway?
How foundation is designed, Column design and beam design
in the earthquqke the profile of water on dam is parabolic or not
Define What is the distance between railway tracks?
How will be cutting in timber plate size 600*400 column size
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?