How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help
Answer Posted / mohammed aijaz hussain
Volume of Wet Mortar = 12 mm X 300 cc.ft.
= 12/1000 X 300/10.76
= 0.335 cu.m.
Add 20% for depressions, joints and wastage:
= 0.067+0.335
= 0.402 cu.m.
Volume of Dry Mortar = 1.3 X 0.402
= 0.523 cu.m. = 18.45 cu.ft.
| Is This Answer Correct ? | 7 Yes | 1 No |
Post New Answer View All Answers
What is Density of cement, sand & aggregate ?
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
How do you calculate the power of centrifugal pump?
I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
Define What is the tallest man made structure in the world?
20mm thick sand face plaster on walls consisting of 12 mm the backing coat of c.m.(1:3)and 8mm thick finished coat of c.m.(1:1)including scaffolding, watering, finishing etc complete please calculator with methyl et et r u
To pcc 11 ft x 24 ft .How many bags of cement, sand and aggregate required? And for roofing how many cgi sheets required?
crank types
TELL US ABOUT A TIME WHEN YOU FAILED TO MEET A DEAD LINE. WHAT WERE THE REPERCUSSIONS?
What is braced excavation all about?
How can i do RCC rate analysis?
i have to give lap joint fo 1Mtr steel of dia12mm,whenever i did mistake i cut less 5cm plz tell me how much i will give lap joint so that length comes 1Mtr
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot