Volume of Wet Mortar = 12 mm X 300 cc.ft.
= 12/1000 X 300/10.76
= 0.335 cu.m.
Add 20% for depressions, joints and wastage:
= 0.067+0.335
= 0.402 cu.m.
Volume of Dry Mortar = 1.3 X 0.402
= 0.523 cu.m. = 18.45 cu.ft.
| Is This Answer Correct ? | 7 Yes | 1 No |
Post New Answer View All Answers
what is the relation between pitch of steel and depth of slab?
What are the types of slump?
what is the metal ratio in granular subbase coarse for one cum ? And please explain the morth table ...what is the difference between grading 1 , 2, 3 what it means..plz explain
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument
How are freeway bridges built?
what is the permanent solution applied for restoration of leaning tower of pisa?
How to get MEP technical,instaaltion & testing data for interview?
please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order
How much for the BRC lapping in full yield and half yield < and which table to get it ?
How to calculate the load of partion in flat slab if we use brick?