Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how much quantity of blocks, cement and sand is required to
complete 1sq.m of CC Hollow blockwork. Size-16"x8"x8". Also
what is the cement sand ration commonly used?

Answer Posted / balamurugan

1.Qty of Hollow block is 11 to 12 Nos/ sqm
2.For 9" wide wall Cement sand ratio is 1:6 & 4" wide wall
Cement sand ratio is 1:4.

Volume of mortar/Sqm = (No of Blocks required for the size
of without mortar thick -No of Blocks required for the size
of block including mortar thick)x No of Blocks required for
the actual size of block

For 9" wall

No of Blocks required for the size of without mortar
thick=1/(0.40*.20*.20)=62.5
No of Blocks required for the size of block including mortar
thick= 1/(0.41*.21*0.21)=53.31 Nos

Volume of mortar/Cum= [62.5-55.31]x[0.4x0.2*0.2]
=0.115 Cum
Add wastage 30% extra

Volume of mortar/Cum= 0.115*30% =0.150Cum

Cement sand calculation/Cum of Block work:

Ratio 1:6

Cement =[1/7*1440]*.150 =31Kg
Sand =[(6/7)*.15]=0.129Cum =4.55 Cft

Cement sand calculation/Sqm of Block work:

Ratio 1:6

Cement =[1/7*1440]*.15*.23 =7.13Kg
Sand =[(6/7)*.15*.23]=0.03Cum =1.05Cft

Is This Answer Correct ?    80 Yes 39 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the strongest bridge for a school contest?

1126


How much material is required for constructing a 2 Lane 2Km rigid pavement road

2146


What is chemical composion test

2014


How to avoid fly ash seed ball formations in the concrete mixer while mixing of raw materials for fly ash block manufacturing?

1837


manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.

2020


material used for mendrel use to bend epoxy coated rebar

2114


what is the procedure of wet seiving. n percentage of silt in different type of soil?

2591


What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????

2941


howto calculate the quantities of material used in fly ash brick after finding the volume??

1631


03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1

2203


For what building Built-on balconies are preferable? What are the advantages?

1176


How can explode a block?

1085


How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?

1894


What distance in meters on the ground is the equivalent of one second of arc in longitude or latitude?

1055


give me the mix proportion for design mix concrete M 7.5 grade 1:4:8

3977