what is the diffreance between 1 way slab& 2way slab?
Answer Posted / sajin
if the ratio of length to breadth is less than 2 then its an
two way slab and if the ratio is greater than two then it is one way slab.
in one way slab design for the reinforcement ,the
reinforcement provided parallel to the shorter span will be
taking the load and called the main bar and the reinforcement
provided parallel to the longer side will be of smaller dia.
the bar in longer span is called distributer.the crank is only provided for the main bar (ie.bars parallel to shorter span)
in two way slab the reinforcement provided in both span will
be taking load and we have to provide crank for all bars
| Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
How to calculate the quantity of cement mortar 2" for mosaic tile fixing 12"x12"?
what is shuttering co efficient?
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
types of laps in column
How did the romans get water up hills using aqua ducts?
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
What distance in meters on the ground is the equivalent of one second of arc in longitude or latitude?
Define What is the force exerted by the Tacoma narrows bridge?
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
What is the difference in painting using Roller and Brush? What is the paint consumption difference? As per IS one coat of painting is painting from left to right and top to bottom whether this can be done using roller ( Roller Stick height and feasibility) ?
Who built the sears tower?
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?
PL.tell me about civil engineering questions with answer
material required for construction of 1cu.mtr wall (Cement, No of bricks (Brick size 40cm x 20cm x 10cm),sand,Quantity of water