what is the quantity of formwork in shuttering and
barbending is done by 1 mason and 1 helper
Answer Posted / rajesh n s
Shuttering/Formwork Workdone by 1 Carpenter + 1 helper is 5 to 7 Sqm / day
Barbending by 1 Barnender + 1 Helper is 80 to 100 kg / day
| Is This Answer Correct ? | 37 Yes | 5 No |
Post New Answer View All Answers
Define polar co ordinates.
What are the applications of the modulus of elasticity?
Please let me know what is the simplest way of Calculating Mix Designs
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
Define What is Civil Engineering?
Define angular dimension?
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
strength vs shape factor
What are some structures that may be subjected to fatigue?
What is the tallest man made structure in the world?
explain what do you mean by the property development.
what"s the sort of beams?
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
Who built the sears tower?
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.