what is the quantity of formwork in shuttering and
barbending is done by 1 mason and 1 helper

Answer Posted / rajesh n s

Shuttering/Formwork Workdone by 1 Carpenter + 1 helper is 5 to 7 Sqm / day
Barbending by 1 Barnender + 1 Helper is 80 to 100 kg / day

Is This Answer Correct ?    37 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are some facts about concrete?

671


What is the difference between Hinged and pinned in Column ends

4798


What will be weight of 0.5mm GI sheet per sq.ft?

16711


The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it

5570


why does the most of civil engg is not intersted to going for teaching field?

1621






How do you calculate load bearing capacity of a waffle slab?

2225


How many pyramid in egypt?

645


manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.

1372


What is meant by a context menu in a cad software?

690


Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.

1728


What is the primary difference between adsorption and absorption?

735


how many running meters in one kilogram of 4mm pvc coated chainlink fencing

651


For the construction project what capital cost has to be taken in consideration?

681


how much cement and sand consuptin in 4 inch siporex walls 100 sq ft

2518


WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?

1946