what is the quantity of formwork in shuttering and
barbending is done by 1 mason and 1 helper
Answer Posted / kamal mukherjee
Is the question technically correct ? General terminology of shuttering workmen is carpenter and steel fixer ins bar bender .
Again the output is linked to the type of the structure in execution.
Broadly Classified as : Sub structure or Super structure
Detailed Classification: Footing, Raft , Column, beam , slab , decorative work: Cantilever, loft, projection works etc..
general working is 2.5-3 sqm of shuttering and 700-750kgs for bar bending works for a pair of workmen
Is This Answer Correct ? | 8 Yes | 7 No |
Post New Answer View All Answers
Plasterers do how many sqm with spray plaster machine? By hand one mason does 10m2/day. How much they do in Dubai with spray plaster machines?
How to calculate canal slope curvature qty!
in plate load test what is the thickness of plate 20mm 5mm 50mm none
Explain what are the phases inspections are done by local authority while construction?
what are RIB slabs explain about it
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
how to create our resume?
How is calculate the cube molt
What is the snap size in civil and how can we create it?
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
What is the outturn of Ceiling plastering
In block work seawalls what is the purpose of slip joints?
How many Sft of Level Plaster per Kg