how can change 12mmdia@150c/c bar spacing to 16mmdia
Answer Posted / sumit
Suppose known spacing (S1) for Dia (D1)
Define Spacing (S2) for Dia (D2)
So : S2=S1*D2/D1
Then u get answer
| Is This Answer Correct ? | 45 Yes | 36 No |
Post New Answer View All Answers
Explain the advantages and disadvantages of using plastic and timber fenders?
manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
what is the name of shuttering oil used in oman
How much cement,sand,bricks and water needed for 1square metre brick work?
What are the phases inspections are done by local authority while construction?
how u design STAGING for Superstructure in BRIDGE construction?
Explain how you can turn off the display for dimension in CAD?
Define What is Civil Engineering?
List out the potential risk factors for workers on the construction site?
How can i display 5 asterisk and another 5 asterisk )?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What should be the standard roof height like to be?
what is the list of building construction equipment & teir output?
Rate analysis of Vitrified tile in cement mortor 1:3