Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how 1.52 factor comes while calculating no of bags of
cement...from 1:2:4 design mix?

Answer Posted / ajay kumar singh

For 100cum of finished concrete =152cum dry volume of
conc. Hence for 1cum the factor will be 1.52
Calculation of material in 1cum of (1:2:4)conc.
Cement=1.52/1+2+4=0.217cum
Sand=0.217*2=0.434cum
Metal=0.217*4=0.868cum

Is This Answer Correct ?    64 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Formula for calculation volume of essentric footing

1770


what is the price of a cubic meter of concrete on international market?

1168


calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick

1749


How can we make a hole in a solid rectangle using solidsworks?

1208


pls mail some more tecnical qustions at msaranya2610@gmail.com

2051


What glue is least sticky?

1162


Why are steel plates inserted inside bearings in elastomeric bearings?

1108


What are the applications of modulus of elasticity?

1287


How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/

1823


the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none

2125


What is meant by cartesian coordinate system?

1118


what is high type road and low type roads

1604


A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx

1770


How do you compute the volume of airflow?

1065


Explain the different types of building contracts?

1057