Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

WHEN BRICK SIZE IS 3X5X9" , WHAT WOULD BE THE NUMBER OF
BRICK REQUIREMENT FOR 100 SQFT AREA OF 5" width?

Answer Posted / vishnutom

960 Number of bricks are required.

Explanation:

100 Sqft area of 5" wide
as the brick size is given in inches, convert the area in to
inches from sq.ft.

1 ft = 12 inches
1 sq.ft=12^2 sq.inches ie.,= 144 sq.inches
100 sq.ft = 100*144= 14400 sq.inches.

Length of brick = 9"
Width of brick= 5"
Thickness of brick= 3"
but in question it was given that the 100 sqft area of 5"
wide only..
Hence keeping 5" wide side of brick in position of 5" wide
area, Length of area 14400 sq.inches= (LxB=Area)
(L)*5"=14400.
L=14400/5=>2880 inches

No. of bricks= 2880/ht of each brick

Answer:

=> If we keep 3" side of brick along length the bricks
required should be 2880/3=>960 No. of bricks

=> If we keep 9" side of brick along length the bricks
required should be 2880/9=>320 No. of bricks

Check:
1) 320*9"*5"=14400Sq.inches=> 100 Sq.ft
2) 960*3"*5"=14400Sq.inches=> 100 Sq.ft

Is This Answer Correct ?    8 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to increase a bearing capacity of soil?

1179


How much sand and cement requirement for 1 SQM 125mm thickness Brickwork

4553


Formula for calculating the volume of bulb in underreamed pile

5067


What is Critical path in Ms-Project ?

1247


My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).

3100


How do you calculate reinforcement weight of steel?

1147


Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?

2177


What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster

2356


Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.

2395


What things you need to take care of before building a kitchen island?

1243


how much required strength of cement concrete bricks(size 230x115x75mm)

2043


who to find building iron rod strenth

2234


Explain different types of rcc pipes.

1209


The concrete slump recommended for beams and slabs; is?

1319


what is the maximum number of course that can be laid according to IS code and the max height.

2137