Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.

Answer Posted / sumanth

we can only calculate the quantity in m3 only after that we
can converet in c.ft.
1/4 x 1.54 x 28.8= 11.08 bags cement for 1 m3 for the ratio
of 1:1:2
s0 731 cft = 20.719 m3 * 11.08 = 229.570 bags cement used
1/4 x 1.54 = .385 m3 sand for 1 m3
so 20.719 m3 x .385 = 7.976 m3 sand required in 731 cu .ft
2/4 x 1.54 = 0.77 m3 chips ( aggregate ) for 1 m3
so 20.719 m3 x 0.77 = 15.953 m3 chips required in 731 cu .ft

Is This Answer Correct ?    15 Yes 10 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2

2033


Specific gravity of cement?

1709


How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?

8067


WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?

3280


What are the advantages of cad software?

1172


What is the largest concrete dam in the world?

1239


which type of instrument included in plumbing work?name of instrument?

2191


What are the different approaches in designing the floors of the service reservoirs?

1229


How can i do RCC rate analysis?

1737


types of laps in column

2426


What is difference between combin footing & rapt footing

2044


why top layer of block work shoud be full size if any cut block adjustable than another layer?

2258


what pressure the NP2 class RCC pipe can sustain?

2758


4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils

2888


I need old MMUP exam question and answer for Civil engineering

1666