Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Why capacitor bank does not require in DG Set?

Answer Posted / sudip sengupta

DG's are normally designed for P.F. of 0.8 lag. If the P.F.
of the load is more than 0.8, we should not use capacitor
bank as the current draws by the capacitor will increase
the KW demand of the DG. But if the load has P.F. less than
0.8, we can use capacitor bank to improve it to 0.8 or
slightly above.

Is This Answer Correct ?    0 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is a diode?

1115


number of I/O devices in siemense plc

2203


how to design coil turns ?

2028


how to measure the transformer resistance values(dyn11)?and howmuch the minimum value?

2191


what is the relationship between phase & neutral

2641


How to calculat the ratio of HT\LT in energy meter

2758


can we synchronize star system generators with delta system transmission line ? and how ?

2882


what is the difference between an alternator and a synchronous motor

2072


The simple way of finding the leakage quantity and % in compressed air distribution system

1719


hr round

2193


Mention the disadvantages of low power factor? How can it be improved?

1201


Why let through energy not considered for ACB breaker while cable sizing?

2469


what happens to the supply voltage if there is any change in frequency?

6549


how dia of wire and angles are calculated for overhead shielding wire to protect substation equipment from lightening strokes???

2083


WHTA IS LIMT OF LEAKGE CURRENT OF 11 KV 1 CORE 1000SQ.MM. XLPE CABLE.LOAD ON CABLE IS AROUND 600AMP .LENGTH 500 MTRS.

2211