An 11kv system consisting of an underground cable to a sub
station about 300 meters away was shut down for about 10
hrs. On energising, it tripped off on earth fault about
10---20 mins later 6 times but since than it is not
tripping.its already 3 weeks now. The SPAJ was found to be
fine. what could be the cause.No test had been done to
determine the cause of the trippings till now because of
demand.
Answer Posted / pillay
thanks but I had managed to ON the system and remained
energized with some load for a few minutes (10 -20 mins)
before it tripped again on earth fault , it happened 6 times
on (4/6/2011) and till today (13/07/2011) no problem. we
are using ABB spaj oc/ef relay.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How can we calculate the KVA rating of a Distribution transformer from its core details?
What is the procedure/activities to be taken to inject the current more than 2000A by using 2000A Loading Transformer?
what is Anti-pumping?
1.WHAT IS A SMART CAPABLE DB ( DISTRIBUTION BOX) ? 2. HOW TO DECIDE THE TYPE OF DB TO BE USED ( RECESSED/ PLUG TYPE/ SMART ETC ETC? 3. WHAT IS MILLENEUM BUS BAR USED IN DB? 4.DIFFERENTIATE MCCB AND MCB.
Why the earth to phase voltage is high 250 compare to other two phases
How to size Air Circuit breaker (ACB)? What is the most important factors?
Please elaborate th´evenin’s theorem?
Differentiate between Zero and Negative sequence current
earth also having a gravitational force (magnetic field of north and south)but it attracts any object compare to this theartifical magnetic cant perform same as earth why?
What are the uses of lead compensator?
What is MSL designation of a motor and same may be provided in details.
SUTIABLE FOR ohm's law super conductor
What are the advantages of speed control using thyristor?
How to select the proper VSD to operate high inertial load
What is effect of over voltage and under voltage on ACB