How to find out the quantity of steel FE415
Answer Posted / mohammed mohiddin
1. Unit wt of steel Ws = 0.785 kg/cm^2/meter length.
2. Crossectional Area (As) of steel can be found using
formula
As = pi x d^2/4
where d = dia of rebar in cm.
3. Now, wt of steel = Ws x As kg/m
Eg:
Take,
d = 16 mm
Wt of steel per meter lenght = 0.785 x 3.1428 x (1.6)^2/4
= 1.58 kg/ meter length of bar
This can be simplified for calculation as below:
Wt of steel = square of dia in mm/162 (kg/ meter length)
Note:- This is very simple method where we must remember to
mention dia in millimeter to get result in kg per
meter length of rebar.
...Good luck...
| Is This Answer Correct ? | 22 Yes | 1 No |
Post New Answer View All Answers
what are the five benefits of using standard terminology in the measurement process?
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
what is tension column?
Is it necessary to apply tack coat over the primecoat. IF not what happens.answers other than 1.to superimpose the next layer(2) to adhere the layers so as to form homogenity.
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
How you can use different dimension tools in cad? What are the different dimensions available?
how to convert cement, sand aggregate quantity from M3 to kg with full description?
How many square meter can a worker/labor demolish a structure per day?
how to calculate reinforcment in staircase cranked beam?
how water proof chemicals act in concrete to avoid leek?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
how to shuttering is used in slab
Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?
What is Time period of a building and its relation with frequency ?