Cube tests of concrete are failed at 7 days and 28
days.What is your next action?
Answer Posted / vimalsekar
Well. When Concrete cube test result fails at 28th day then
go for concrete core cutting and check the compressive
strength in it. Number of cores shall be as per the
engineer incharge's decision but should not be less than 3
nos. IS:456 says if the core test fails then go for load
test. IS : 456 also says that NDT can be done . But with
rebound hammer test only surface hardness will be known and
hence this test result is not reliable and hardly anyone
suggests for this test.
Is This Answer Correct ? | 18 Yes | 3 No |
Post New Answer View All Answers
Formula for calculating the volume of bulb in underreamed pile
Explain what are the problems one might face while having a Cantilever balcony?
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
what is the use of beam end forces while using a staad ? wha they are show
What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code
Explain soil analysis?
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
can stub column take the load as main column
pls tell me , what is the water content
What is missing report and how to prepare
How to make a c++ program that converts any base to base 10?
Basic civil interview questionsÂ
Prepare a Schedule for a Highrised building from starting stage to Handover?
How to find the cuplock pipe qty in staging for Minor bridge?
How many feet are in 4 square yards?