Answer Posted / arindam chatterjee
tension is on the inner side at the ends of the walls so
reinforcement should be given on the inner side to prevent
seepage of water.nd outer reinforcement must be provided on
the middle of the walls.the base slab can be designed as a
slab only by redistributing the moments.design must be done
for maximum moment only.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
what discoveries did you have in relation to your course?
Any strength is a stress but any stress is not strength
minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?
how do you calaculate the total steel quantity of an rcc building using thumb rule?
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
what r you reqired for concrete baching plant?
sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
TELL US ABOUT A TIME WHEN YOU FAILED TO MEET A DEAD LINE. WHAT WERE THE REPERCUSSIONS?
what is Brest Wall?
what is the breaking strength of wall tiles
Why was the empire state building made of steel?
If we don't have drawing for Excavation of building,At what rule we will go for excavation and how much depth will go for a villa?
What do you mean by honeycomb in concrete?
how can we calculate steel value, depending on load